# Monte Carlo Forecasting

Monte Carlo forecasting repeatedly samples historical delivery data to estimate probability ranges for how much work may finish or when a body of work may complete.

- Type: method
- Domain: Delivery & agility
- Level: Advanced
- Last reviewed: 2026-09-22
- Original: [Soroush’s Product Wiki](<https://wiki.soroush.uk/topic/monte-carlo-forecasting/>)

## What it means

Monte Carlo forecasting runs many randomized simulations using observed delivery data. A how-many forecast estimates the number of items likely to finish by a date; a when forecast estimates completion dates for a specified number of items. Results are expressed as probability percentiles, not a single guaranteed date or quantity.

## Why it matters

Delivery work varies, and a simple average discards that variation. Simulation retains the range found in representative historical observations and makes uncertainty discussable. Stakeholders can compare options such as an 85-percent date versus a 95-percent date, then choose based on risk appetite rather than receiving false precision.

## When to use it

Use Monte Carlo when a team has sufficient relevant cycle-time or throughput history and needs a probabilistic delivery forecast. It suits release, backlog, and service-level questions. Reconsider the input sample when team composition, workflow, item mix, demand, or completion policy changes enough that old data no longer represents the future.

## How it works

1. Frame one clear question: how many items by a date, or when a defined number of items may finish.
2. Select a representative historical data set, preserving low-output periods and legitimate outliers.
3. Run thousands of trials by repeatedly sampling throughput or cycle-time observations according to the model.
4. Summarize outcomes as percentile dates or quantities and state the data window, assumptions, and scope rules.
5. Update the forecast as work completes or conditions change, and pair it with explicit risk decisions.

## A practical example

A team has 60 comparable migration items remaining and 20 weeks of throughput data. Simulation suggests completion by November 6 at 70 percent confidence, November 20 at 85 percent, and December 4 at 95 percent. Leaders choose the 85-percent planning date and fund a fallback rather than presenting November 20 as certain.

## Where it breaks

Simulation cannot rescue unrepresentative or poor-quality data. It assumes sampled history is relevant and usually does not model every dependency, scope change, item-size shift, or rare disruption. Confidence percentages describe the model's outcomes, not certainty about reality. Cherry-picking recent good weeks produces deceptively optimistic forecasts.

## Common mistakes

- Feeding estimates into a model while presenting the output as evidence from actual delivery performance.
- Removing zero-throughput periods or inconvenient outliers solely to improve the forecast.
- Communicating one percentile date as a promise without assumptions, alternatives, or ongoing updates.

## Visualization

[View the visualization on the website](<https://wiki.soroush.uk/topic/monte-carlo-forecasting/#visualization-monte-carlo-forecasting>)

## Sources

1. [Forecasting Resources](<https://prokanban.org/forecasting-resources>) — ProKanban.org · Professional resource collection
2. [Probabilistic Forecasting and Flow with Scrum](<https://scrumorg-website-prod.s3.amazonaws.com/drupal/2024-05/Probabilistic%20Forecasting%20and%20Flow%20with%20Scrum%20-%20Whitepaper.pdf>) — Scrum.org · Professional white paper

## Related topics

- [Throughput](<https://wiki.soroush.uk/topic/throughput/>)
- [Cycle Time](<https://wiki.soroush.uk/topic/cycle-time/>)
- [Burnup Chart](<https://wiki.soroush.uk/topic/burnup-chart/>)